**9/4/03** Upton Bypass Works Update

Dorset County Council (DCC) and the Borough of Poole are currently working in partnership on major road resurfacing and bridge waterproofing work to the Upton Bypass between Holes Bay Roundabout and Bakers Arms Roundabout.

The work includes resurfacing of the entire westbound carriageway as well as the eastbound carriageway in Poole. Resurfacing work is also being carried out to the A350 interchange and slip roads as well as re-waterproofing of the bridges associated with the Pony Drive and A350 junctions.

For safety, a 40mph speed limit remains in force while lane and slip road closures are implemented. Some disruption to the travelling public will be inevitable and allowances should be made for additional journey times on both the Bypass and alternative routes.

The current provisional (weather dependent) programme is indicated below.

 

Date

Work

Traffic Management

1

Ongoing

  • Complete the re-surfacing of A350 junction
  • Sign and safety fencing work
  • Reinstate crossover at Holes Bay Roundabout
  • A350 junction: Eastbound carriageway slip roads closed Thursday and Friday (10th and 11th). On-slip will remain open for morning peak traffic on Thursday only
  • Lane closures remain around A350 junction until Wednesday 16th
  • Lane closures at times on various sections of Bypass (off-peak only between Holes Bay and Upton House junctions)

2

Works complete by end of Wednesday 16 April – weather permitting

For further information, please contact:

Keith Calder - Borough of Poole - (01202) 262233
Richard Bastow - Dorset County Council - (01305) 225335